Projects/Schemes Under Planning
Lucknow Housing Scheme: Project
completed. Registration of Title Deed of individual dwelling unit/flat and/or
parking, (if allotted) has been commenced in co-ordination with the Kendriya
Vihar Apartments Welfare Society (KVAWS), Lucknow in Jan 2010. Click for [Draw Result and Waiting list status] [Registration Details].
Chennai
(Phase-II) Housing Scheme: Scheme fully subscribed. Fourth instalment
called with 13th Mar 2009 as the last date of payment. A letter regarding
revision of the DU cost has been despatched to all beneficiaries. Fifty percent
of the increase in announced cost of dwelling units, as informed vide our
letter no. A-507/2 dated 06/08/09 has already been called with 09/10/09 as the
last date of payment. Remaining increased amount shall be called alongwith 5th
and 6th instalments @ 25% each. Click for
[Letter dated 26/08/10 regarding applicability of
Service Tax] [Letter dated 07/05/10] [Cost revision letter dated 06/08/09] [Waiting
list status] [Plans approval letter] [Latest Photo] [List of Defaulters].
Hyderabad
(Phase-III) Housing Scheme: Scheme
fully subscribed. Fourth instalment called with 7th Sep 2009 as the last date
of payment. A letter regarding revision of the DU cost has been despatched to
all beneficiaries. Fifty percent of the increase in announced cost of dwelling
units, as informed vide our letter no. A-402/11 dated 24/07/09, is being called
shortly. Remaining amount shall be called alongwith 5th and 6th instalments.
Click for [Letter dated
26/08/10 regarding applicability of Service Tax] [Cost revision letter dated 24/07/09] [Waiting
list status] [Latest Photo] [List
of Defaulters].
Pimpri
Chinchwad, Pune (Phase-II) Housing Scheme: Project Completed. A letter to
all (Ph-II) beneficiaries has been dispatched, date of meeting 27/06/10. Click for
[Draw Result and Waiting list status]
[Copy of Letter] [Letter
regarding Registration].
Mohali
(Phase-I) Housing Scheme: Fifth instalment has been called with 7th May
2010 as the last date of payment. Click for [Letter dated
26/08/10 regarding applicability of Service Tax] [Latest Photo]
[Technical Brochure] [List of Defaulters] [Waiting list status].
BHUBANESWAR (Ph-I) Housing Scheme: Scheme fully subscribed. Fourth instalment called
with 08th Oct 2010 as the last date of payment. Construction progressing.
Technical Brochure despatched to all the beneficiaries. Click for [Letter
dated 26/08/10 regarding applicability of Service Tax] [Waiting list status] [Plan Approval
Letter] [Latest Photo] [List of
Defaulters] [Interim costing letter dated 17/05/10.].
MEERUT
(Ph-I) Housing Scheme: Scheme was
announced during end’ 2007. Project plans approved. Construction is
progressing. Third instalment called with 1st Oct 2010 as the last date of
payment.
Scheme is now open for
GENERAL PUBLIC on First Come First Serve basis. (subject to payment
of Equalisation Charges at the end of project, as per the CGEWHO Rules). Click for [Letter
dated 26/08/10 regarding applicability of Service Tax] [Advertisement] [Scheme Brochure] [Application Form] [Location
Map] [Plan Approval Letter] [Equalisation Charges] [List of
Defaulters].
JAIPUR (Ph-II) Housing Scheme: Scheme was announced during early’ 2008. Construction
progressing. Fourth instalment called with 22nd Jan 2010 as the last date of payment. Technical Brochures
despatched to all beneficiaries.
Scheme is now open for GENERAL PUBLIC on First Come First
Serve basis. (subject to
payment of Equalisation Charges at the end of project, as per the CGEWHO
Rules). Click for [Letter
dated 26/08/10 regarding applicability of Service Tax]
[Advertisement] [Waiting
list status] [Scheme Brochure] [Application Form] [Location Map] [Latest
Photo] [Plan
Approval Letter] [Equalisation Charges] [List of Defaulters] .
Vishakhapatnam Housing Scheme: Scheme announced on 09th Oct 2008 was under-subscribed
and, hence, is currently Re-Planning stage and open for GENERAL PUBLIC on FIRST
COME – FIRST SERVE basis (subject to payment of Equalisation Charges at the end
of project, as per the CGEWHO Rules). Click for [Letter
dated 26/08/10 regarding applicability of Service Tax] [Location Map]
Bhubaneswar
(Ph-II) Housing Scheme:
Scheme announced with 26/02/2010 as the last date for applying. Scheme
over-subscribed and closed. Computerised Draw held on 19/05/10. The refund of
unsuccessful applicants is in progress. Click for [Letter
dated 26/08/10 regarding applicability of Service Tax] [Allotment / Waiting List] [Location
Map] [Key Plan of the Project].
Kolkata
(Ph-II) Housing Scheme: Scheme now open on FIRST
COME – FIRST SERVE basis for Priority-I & II applicants only.
Click for [Advertisement] [Scheme Brochure/Application
Form] [Cover Pages / Location Map].
Formal acknowledgement (by email or
by post) of the applications received are being sent mentioning Regn. No(s) who
will be offered confirmed allotment, after encashment of Demand Draft (EMD)
within three months.
Note: a) In case your
Employer/ Financial Institution requires a copy of the Sale/ Lease deed of the
land for extending housing loan facility, you are requested to email such a
requirement enabling us to forward the same in an electronic form (to be
downloaded at your end).
b)
If you are facing problems in viewing and printing PDF files, please download
the full PDF file to your local system and launch the Acrobat Reader against it
directly. This can be done in most browsers by clicking the right mouse button
and then selecting the option to save locally. For example the option in
Internet Explorer is “Save Target As” and in Netscape Communicator it is
“Save Link As.”
c) Beneficiaries are
advised to clear all dues in time. Delay in payment of instalments calls for
penal interest. Part payments are also permitted.
|
Scheme |
No. of DU |
|
Chennai (I) |
524 |
|
Nerul (Navi Mumbai) |
384 |
|
Panchkula (I) |
98 |
|
Sector 51,NOIDA (I) |
692 |
|
Sector 51,NOIDA (II) |
508 |
|
Kharghar (Navi Mumbai) |
1230 |
|
Kolkata (I) |
576 |
|
Gurgaon (I) |
1088 |
|
Chandigarh |
305 |
|
Hyderabad (I) |
344 |
|
Kochi (I) |
43 |
|
Bangalore |
603 |
|
Gurgaon (II) |
852 |
|
Pune (I) |
159 |
|
Sector-82, Noida(III) |
980 |
|
Noida (IV) |
720 |
|
Ahmedabad |
310 |
|
Hyderabad (II) |
178 |
|
Jaipur |
184 |
|
Panchkula (II) |
240 |
|
Noida (V) |
576 |
|
Lucknow |
130 |
|
Pune (II) |
148 |
|
Total |
10872 |
|
Scheme |
No. of DU |
|
Chennai (II) |
572 |
|
Hyderabad (III) |
380 |
|
Mohali (I) |
603 |
|
Bhubaneswar (I) |
256 |
|
Meerut (I) |
90 |
|
Jaipur (II) |
572 |
|
Vishakhapatnam (I) |
190# |
|
Bhubaneswar (II) |
240 |
|
Kolkata (II) |
690 |
|
Total |
3593 |
|
# Scheme is still substantially undersubscribed. |
|
|
Scheme /Location |
Tentative No.
of DUs |
Remarks |
|
Mohali (II) Kharar, Mohali |
656 |
Scheme expected to be announced in Sep 2010. |
|
Chennai (III) Poonamali-Avadi Road, Chennai |
732 |
Further course of action is proposed to be putup to Executive Committee. |
|
Kharghar (II), Navi Mumbai |
625 |
Land yet to be transferred in favour of CGEWHO. |
|
Greater Noida Sector P-4, Greater Noida (behind Senior Citizen’s Home) |
1300 |
Lease deed signed and action in hand to select Architect / Consultant for planning the project. |
|
Gurgaon (III) Sector 70, Sona Road, Gurgaon |
- |
In accordance to the decision of Combined reconvened XIX Meeting of General Body(GB) and XXXXIV Meeting of Governing Council(GC), MOU approved by combined GB & GC is to be signed towards returning back the land to the Turnkey Contractor M/s Capital Builders on receipt of agreed value of Rs. 47.55 Crores. |
|
Meerut (II) |
600 |
Rs. 2.2 crore paid to MDA. Balance approx. 12 crore to be paid to acquire the land. |
|
Mohali (III), PUDA Land |
226 |
Land taken over and action shall be progressed towards selection of Architect. |
|
|